Bakewell Bridge [20]

Bakewell Bridge Replacement [20] [Nov - Dec 2007]
path-05  Shared bicycle and foot path to the underpass in Henley Beach Road. Saturday 10 November 2007. panel01  Decorative concrete wall panels on the underpass beneath James Congdon Drive. Saturday 10 November 2007. under 01  View of the underpass from Henley Beach Road. Saturday 10 November 2007. under 02  View of the underpass from Henley Beach Road. Saturday 10 November 2007.
under 03  View of the underpass from Henley Beach Road. Saturday 10 November 2007. under 04  View of the underpass from Henley Beach Road. Saturday 10 November 2007. henley30  Underpass site, seen from Henley Beach Road. Thursday 15 November 2007. henley31  Small roller by the underpass in Henley Beach Road. Thursday 15 November 2007.
henley32  Approach to underpass in Henley Beach Road. Thursday 15 November 2007. henley33  Road works on the underpass approach in Henley Beach Road. Thursday 15 November 2007. henley34  Underpass approach from Henley Beach Road. Thursday 15 November 2007. pave-12  Asphalt paving of the underpass beneath James Congdon Drive and the rail lines. Thursday 15 November 2007.
pave-13  Asphalt paving of the underpass beneath James Congdon Drive and the rail lines. Thursday 15 November 2007. pave-14  Asphalt paving of the underpass beneath James Congdon Drive and the rail lines. Thursday 15 November 2007. pave-15  Asphalt paving of the underpass near James Congdon Drive and the rail lines. Thursday 15 November 2007. pave-16  Asphalt paving of the underpass beneath James Congdon Drive and the rail lines. Thursday 15 November 2007.
pave-17  Asphalt paving of the underpass beneath James Congdon Drive and the rail lines. Thursday 15 November 2007. pave-18  Asphalt paving of the underpass beneath James Congdon Drive and the rail lines. Thursday 15 November 2007. jcd-27  Bridge footpath in James Congdon Drive, with parapet railings ready for installation. Thursday 15 November 2007. block-04  Crane positioning sections of concrete barrier in Henley Beach Road. Thursday 22 November 2007.
block-05  Crane positioning sections of concrete barrier in Henley Beach Road. Thursday 22 November 2007. block-06  Crane positioning sections of concrete barrier in Henley Beach Road. Thursday 22 November 2007. block-07  Crane positioning sections of concrete barrier in Henley Beach Road. Thursday 22 November 2007. block-08  Sections of concrete barrier in Henley Beach Road, near James Congdon Drive. Thursday 22 November 2007.
formwork  Installing formwork for the remaining section of parapet wall on the underpass approach at Henley Beach Road. Saturday 1 December 2007. ga-19  Paving of the underpass approach in Glover Avenue. Thursday 22 November 2007. ga-20  Constructing road base on the approach in Glover Avenue. Thursday 22 November 2007. ga-21  Constructing road base on the approach in Glover Avenue. Thursday 22 November 2007.
ga-22  Constructing road base on the approach in Glover Avenue. Thursday 22 November 2007. ga-23  Constructing road base on the approach in Glover Avenue. Thursday 22 November 2007. ga-24  Concrete pump in Glover Avenue, near West Terrace. Thursday 22 November 2007. ga-25  Underpass approach in Glover Avenue. Saturday 1 December 2007.
ga-26  Paving the underpass approach in Glover Avenue. Saturday 1 December 2007. ga-27  Paving the underpass approach in Glover Avenue. Saturday 1 December 2007. ga-28  Paving the underpass approach in Glover Avenue. Saturday 1 December 2007. ga-29  Road works on the underpass approach in Glover Avenue. Saturday 1 December 2007.
ga-30  Road works in Glover Avenue, near West Terrace. Saturday 1 December 2007. ga-31  Road works in Glover Avenue, near West Terrace. Saturday 1 December 2007. henley35  View of the Henley Beach Road approach, from James Congdon Drive. Thursday 22 November 2007. henley36  View of the Henley Beach Road approach, from James Congdon Drive. Thursday 22 November 2007.
henley37  View of the Henley Beach Road approach, from James Congdon Drive. Thursday 22 November 2007. henley38  Paving of the underpass approach at Henley Beach Road. Saturday 1 December 2007. henley39  Paving of the underpass approach at Henley Beach Road. Saturday 1 December 2007. henley40  Paving of the underpass approach at Henley Beach Road. Saturday 1 December 2007.
henley41  Paving of the underpass approach at Henley Beach Road. Saturday 1 December 2007. henley42  Paving of the underpass approach at Henley Beach Road. Saturday 1 December 2007. henley43  Paving of the underpass approach at Henley Beach Road. Saturday 1 December 2007. jcd-28  Bridge footpath in James Congdon Drive, with parapet railings installed. Thursday 22 November 2007.
jcd-29  Bridge footpath in James Congdon Drive, with parapet railings installed. Thursday 22 November 2007. jcd-30  Footpath south of the road bridge under construction in James Congdon Drive. Thursday 22 November 2007. jcd-31  Painted parapet wall on road bridge in James Congdon Drive. Thursday 22 November 2007. jcd-32  Underpass beneath the rail bridge, seen from James Congdon Drive. Saturday 1 December 2007.
jcd-33  Underpass beneath the rail bridge, seen from James Congdon Drive. Saturday 1 December 2007. paint5  Painting the concrete barrier in Henley Beach Road. Thursday 22 November 2007. paint6  Painting the parapet wall and beam of the overpass above Henley Beach Road. Thursday 22 November 2007. paint7  Painting the parapet wall and beam of the overpass above Henley Beach Road. Thursday 22 November 2007.
paint8  Painting the parapet wall and beam of the overpass above Henley Beach Road. Thursday 22 November 2007. parapet1  Parapet wall and railing on the underpass approach in Henley Beach Road. Saturday 1 December 2007. parapet2  Parapet wall and railing on the underpass approach in Henley Beach Road. Saturday 1 December 2007. parapet3  Parapet wall and railing on the underpass approach in Henley Beach Road. Saturday 1 December 2007.
parapet4  Parapet wall and railing on the underpass in Henley Beach Road and James Congdon Drive. Saturday 1 December 2007. path-06  Shared bicycle and foot path from the underpass to James Congdon Drive and Henley Beach Road. Saturday 1 December 2007. rb08  Nearly painted parapet wall on the rail bridge above Henley Beach Road. Thursday 22 November 2007. rb09  Nearly painted parapet wall on the rail bridge above Henley Beach Road. Thursday 22 November 2007.
rb10  Rail bridge above the underpass, seen from Glover Avenue. Thursday 22 November 2007. rb11  Rail bridge and paving work in Glover Avenue, seen from James Congdon Drive. Saturday 1 December 2007. rb12  Rail bridge, with a passing north-bound freight train, seen from near Glover Avenue. Saturday 1 December 2007. under 05  View of the underpass from Henley Beach Road. Thursday 22 November 2007.
under 06  View of the underpass beneath the rail bridge, from James Congdon Drive. Thursday 22 November 2007. under 07  View of the underpass looking east from Henley Beach Road. Saturday 1 December 2007. under 08  View of the underpass looking east from Henley Beach Road. Saturday 1 December 2007. under 09  View of the underpass looking east from Henley Beach Road. Saturday 1 December 2007.
under 10  View of the underpass looking east from Henley Beach Road. Saturday 1 December 2007. wt8dec1  Road works in Currie Street, near West Terrace. Saturday 8 December 2007. wt8dec2  Road works in Currie Street at West Terrace, in preparation for Glover Avenue reopening. Saturday 8 December 2007.